What is a method statement?

A method statement is a document that sets out, step by step, how a particular job will be done safely. It says who will do the work, in what order, with what equipment, and what precautions will be in place at each stage. On construction sites it usually sits alongside a risk assessment — together they're known as a RAMS.

Method statement vs risk assessment

Risk assessmentMethod statement
AnswersWhat could go wrong, and how likely and serious is it?How exactly will we do this job safely?
FormatHazards, who could be harmed, controls, risk ratingA numbered sequence of work, with the controls built into each step
Written forThe employer and anyone checking the risks are controlledThe people doing the work, and the principal contractor approving it
Legal positionRequired by law for every employerNot named in law, but commonly required by clients and principal contractors

The risk assessment identifies the hazards; the method statement shows how the work is organised so those hazards are controlled in practice.

Is a method statement a legal requirement?

No UK law uses the words "method statement". But the law does require you to assess the risks of your work (Management of Health and Safety at Work Regulations 1999, regulation 3), and on construction projects contractors must plan, manage and monitor their work so it is carried out safely (Construction (Design and Management) Regulations 2015). A method statement is the usual way to show you have done that planning.

In practice, most principal contractors and many clients won't let you start on site without one. So for trades working on other people's projects, it is a document you need, whatever the strict legal position.

What to include

  1. Document control — your company, the client, the site address, a reference, who wrote it and who approved it, and the date.
  2. Scope of works — exactly what you are doing, and what you are not.
  3. Programme — start date, duration and working hours.
  4. People and competence — who is doing the work, their role, and the training or cards they hold.
  5. Sequence of works — numbered steps, in order, with the safety controls for each step.
  6. Plant, equipment and tools — and how they are checked.
  7. PPE — what is needed and when.
  8. Hazardous substances — with reference to any COSHH assessments.
  9. Permits and isolations — for example hot works or electrical isolation.
  10. Emergency arrangements — first aid, nearest A&E, fire procedure, assembly point.
  11. Welfare — toilets, washing, drinking water and rest areas.
  12. Briefing record — signatures to show everyone has read and understood it.

Method statement example: fitting kitchen units

A short worked example for a two-person joinery job in an occupied house. A real method statement would carry the document control, people and emergency details above it.

StepActivitySafety controls
1Arrive, sign in with the client, agree the work areaWork area kept separate from the household; children and pets kept out
2Brief the team on this method statementEveryone signs the briefing record before starting
3Check walls for hidden cables and pipesCable and pipe detector used before any drilling
4Fit wall unitsTwo-person lift; units fixed before releasing; stable step-up used, not a chair
5Fit base units and levelLifting from the knees; heavy units carried empty
6Cut and fit worktopsCutting outside or with dust extraction; FFP3 mask and eye protection; router used only with the jig clamped
7Clean down and remove wasteOffcuts removed daily; walkways kept clear; tools not left unattended

How to write one in six steps

  1. Do the risk assessment first, so you know the hazards you need to control.
  2. Walk through the job from arrival to clean-up and write each step down in order.
  3. Next to each step, write the controls that make it safe — not general statements, but what the team will actually do.
  4. List the people, equipment, PPE and any permits needed.
  5. Add emergency and welfare arrangements for that site.
  6. Brief the team, get signatures, and update it if the job changes.

Templates

Our method statement template is an editable Word file with every section above laid out. If the principal contractor wants the risk assessment and method statement in one document, use the RAMS template. New to RAMS? Read what a RAMS document is. Rather not write one yourself? Our RAMS generator builds a completed RAMS in Word, method statement included, from your answers.

This guide is general information, not health and safety advice. You are responsible for assessing the risks of your own work.

Need the finished document, not just the guide?

Answer a few questions about the job and get a completed RAMS in Word, ready to send — £19 including VAT, supplied straight after payment.

Build my RAMS — £19

Also as editable Word files, £9 each: Method statement template · Health and safety policy template.