Demolition risk assessment

In law demolition is treated the same as any other construction work, so the Construction (Design and Management) Regulations 2015 apply in full. HSE's guidance centres on one risk above all: an uncontrolled collapse. The method of demolition has to be written by a competent person, take account of every hazard of the structure and site, and keep debris inside a defined zone. This page sets out the hazards and controls a demolition risk assessment should show.

Based on HSE — Demolition, read 2026-10-19. This page is a starting point you must adapt to your own site, people, equipment and the client's rules. It is not a substitute for an assessment by a competent person.

Hazards and controls

HazardWho is at riskControls
Uncontrolled or premature collapseOperatives, public, neighbouring buildingsMethod and sequence based on full knowledge of the structure — its form, condition, load paths, stability-sensitive elements and past alterations; elements not critical to stability removed first; reviewed by a competent engineer before work starts.
Debris leaving the sitePublic, road users, neighboursExclusion and debris zones sized to the technique and the distance debris can fall; top-down demolition on confined sites; scaffolding never relied on to shrink the exclusion zone or to support the structure unless designed to.
Asbestos in the structureOperatives, publicRefurbishment or demolition survey by a competent surveyor provided by the client before work starts; asbestos dealt with before the structure is demolished.
Live services in the work areaOperativesInformation on live services, alterations below ground and nearby structures provided as pre-construction information; services isolated and confirmed before demolition.
Falls from heightOperativesNeed to work at height removed where possible — for example a high-reach machine with a protected cab; edge protection where people must work at height.
Dust, noise and vibrationOperatives, neighboursEscape of dust and debris limited; COSHH, noise and vibration assessed for the methods used.
Plant and vehicle movementsOperatives, publicTraffic management plan for the site and its access; segregated routes; banksman for reversing plant.

Method statement — sequence of work

  1. Pre-construction information collected: demolition survey, asbestos, structural stability, services and nearby structures; notice given to the local authority at least 6 weeks before starting.
  2. Demolition method written by a competent person, reviewed by a competent engineer, documented in the plan of work and communicated to the team.
  3. Exclusion, debris and safe working zones set out and adjusted as the work progresses; services isolated; asbestos dealt with.
  4. Work carried out in the planned sequence under supervision; the method revised if the structure differs from what was expected.

What to include in the written assessment

Demolition operatives who move from self-employed work into a PAYE site job can read how to tell HMRC they have stopped being self-employed when they make the switch.

Get the document

Download the free risk assessment template (Word) and fill in the table above for your job, or have the RAMS generator produce a completed risk assessment and method statement for this trade in Word for £19.

Questions

Who writes the demolition method?

HSE says the method must be written by a competent person, take account of all hazards and risks of the structure and site, and control them. A competent engineer should review it before work starts.

Do I need to tell the council before demolition?

Yes. HSE's guidance is that notice must be given to the local authority, usually building control, at least 6 weeks before demolition starts. The council may set pre-demolition requirements, sometimes called a section 81 notice.

Need the finished document, not just the guide?

Answer a few questions about the job and get a completed RAMS in Word, ready to send — £19 including VAT, supplied straight after payment.

Build my RAMS — £19

Also as editable Word files, £9 each: Method statement template · Health and safety policy template.