Trenches and excavations kill by collapse, by what falls in and by what is already in the ground. HSE's position is blunt: no ground can be relied upon to stand unsupported in all circumstances. This page sets out the hazards a competent person would expect to see on an excavation risk assessment, the controls that go against each one, and the inspection routine the Construction (Design and Management) Regulations 2015 require.

Based on HSE — Excavations, read 2026-10-18. This page is a starting point you must adapt to your own site, people, equipment and the client's rules. It is not a substitute for an assessment by a competent person.

Hazards and controls

HazardWho is at riskControls
Collapse of the sidesWorkers in the excavationDecide on temporary support (trench sheets, boxes or shoring) before digging, or batter the sides to a safe angle — considerably flatter in wet ground. Never rely on ground standing unsupported.
Falling or dislodged materialWorkers in the excavationEdge protection such as toeboards or projecting trench sheets; spoil and loose material kept well back from the edge; head protection worn.
Plant and vehicles near the edgeWorkers in the excavation, driversKeep plant and vehicles away from the sides — extra loading raises the collapse risk. Stop blocks where tipping is needed; banksman for reversing plant.
Underground services (gas, electricity, water, telecoms)Operatives, publicLocate services from plans and a cable avoidance tool before breaking ground; hand-dig trial holes near services; treat every cable as live.
Overhead power linesPlant operators, everyone nearbyPlan the work to avoid lines where possible; goalposts and barriers where plant must pass beneath them.
Water entering the excavationWorkers in the excavationSupports designed for groundwater; water channelled to sumps and pumped; de-watering methods considered at planning stage.
People and vehicles falling inOperatives, public, site visitorsSubstantial barriers and covers; the excavation fenced off out of hours; lighting where the public pass.

Method statement — sequence of work

  1. Service search and permit to dig completed and signed before any machine breaks ground.
  2. Support or batter system chosen from the ground conditions and depth, and the materials on site before digging starts.
  3. Spoil placed at least the depth of the trench away from the edge; access by ladder, tied and extending above the edge.
  4. A competent person inspects at the start of every shift and after any event affecting stability (rain, nearby loads, a strike); faults corrected immediately and the inspection recorded.

What to include in the written assessment

Get the document

Download the free risk assessment template (Word) and fill in the table above for your job, or have the RAMS generator produce a completed risk assessment and method statement for this trade in Word for £19.

Questions

How often must an excavation be inspected?

At the start of each shift in which people will work in it, and after any event likely to have affected its strength or stability. The inspection is by a competent person and recorded.

At what depth does a trench need support?

HSE does not set a safe depth. Any excavation may need support depending on the ground, water and loads next to it — the decision is made before digging, not after.

Need the finished document, not just the guide?

Answer a few questions about the job and get a completed RAMS in Word, ready to send — £19 including VAT, supplied straight after payment.