Mobile tower scaffold risk assessment

Aluminium towers are quick to put up and quick to put up wrongly. HSE's tower scaffold guidance is built around one idea: the tower arrives with every component needed to prevent falls and keep it stable, and it collapses when sections are left out. This page lists the hazards for a tower risk assessment and the controls, including the rules for moving it.

Based on HSE — Tower scaffolds, read 2026-10-18. This page is a starting point you must adapt to your own site, people, equipment and the client's rules. It is not a substitute for an assessment by a competent person.

Hazards and controls

HazardWho is at riskControls
Collapse because components are left outUsers, people belowTower built to the manufacturer's instruction manual with double guardrails, toeboards, bracing and an access ladder; stabilisers or outriggers fitted when the manual requires them.
Falls during assembly and dismantlingErectorsErected by trained, competent people using a safe method — the advance guardrail system or the through-the-trap (3T) method.
Overturning while being movedUsers, people nearbyHeight reduced to a maximum of 4 m before moving; pushed or pulled from the base by hand only; never moved with people or materials on it.
Soft, uneven or sloping groundUsersFirm, level ground with castors locked or base plates properly supported; never bricks or blocks under any part; ground checked for potholes before moving.
Contact with overhead power linesUsersOverhead lines and other obstructions checked before the tower is moved or raised.
Strong windUsers, publicNever used or moved in strong winds; tied in or dismantled if left standing.

Method statement — sequence of work

  1. Instruction manual for this make and model on site; the erector and supervisor have read it.
  2. Ground checked and the tower built in the manual's sequence with all guardrails, toeboards and braces fitted before the platform is used.
  3. Inspection after assembly and at suitable intervals by a competent person — every 7 days where a person could fall 2 m or more; the result recorded and kept until the next inspection.
  4. Height dropped to 4 m and the platform cleared before any move; tower never used in strong wind.

What to include in the written assessment

Get the document

Download the free risk assessment template (Word) and fill in the table above for your job, or have the RAMS generator produce a completed risk assessment and method statement for this trade in Word for £19.

Questions

Do you need a PASMA card to use a tower?

HSE requires that towers are erected by people who are trained and competent and points to the PASMA code of practice as one source of that training; it does not name a particular card as a legal requirement.

How often is a tower inspected?

After assembly and then at suitable regular intervals. Where someone could fall 2 m or more during construction work, every 7 days, with each result recorded.

Need the finished document, not just the guide?

Answer a few questions about the job and get a completed RAMS in Word, ready to send — £19 including VAT, supplied straight after payment.

Build my RAMS — £19

Also as editable Word files, £9 each: Method statement template · Health and safety policy template.