Scaffolding risk assessment

A scaffold risk assessment covers two populations: the scaffolders who erect, alter and dismantle it, and everyone who then works on or walks beneath it. HSE expects every scaffold to be built to a recognised standard configuration (NASC TG20 for tube and fitting, the manufacturer's instructions for system scaffold) or to a bespoke design, erected under the supervision of a competent person, and inspected before first use and at intervals of no more than seven days.

Based on HSE — Scaffolds, read 2026-10-18. This page is a starting point you must adapt to your own site, people, equipment and the client's rules. It is not a substitute for an assessment by a competent person.

Hazards and controls

HazardWho is at riskControls
Falls during erection, alteration and dismantlingScaffoldersOnly trained, competent scaffolders; trainees under a trained scaffolder; advance guardrail or other safe erection method; harnesses clipped on where guardrails are not yet in place.
Scaffold outside a standard configurationScaffolders, users, publicUnless built to TG20 or the manufacturer's standard configuration, a bespoke design by calculation from a competent person — and any later change that takes it outside the standard configuration is designed too.
Collapse or overturningUsers, publicTies as the design or TG20 requires; sole boards on soft ground; no removal of ties, braces or boards by other trades; loading kept within the class the scaffold was designed for.
Falling materials and toolsPublic, other trades belowToeboards and brick guards or netting; no stacking above the toeboard; fans or covered walkways where the public pass; exclusion zone during erection and striking.
Unsafe or incomplete scaffold used by other tradesUsersInspection after installation and before first use, then at least every 7 days and after any circumstance liable to affect safety, such as high winds; defects recorded and corrected before use.
Unauthorised access out of hoursPublic, childrenLadders removed or boarded; scaffold alarms or fencing on street-facing scaffolds.

Method statement — sequence of work

  1. Scaffold drawing or TG20 compliance sheet on site before erection; the scaffolder gang leader holds it.
  2. Exclusion zone and signage set out at ground level; erection sequence follows the method in the design or manufacturer's instructions.
  3. Handover certificate issued only after the first inspection; the inspection report records defects and the corrective action even where fixed on the spot.
  4. Weekly inspection booked into the site diary; an extra inspection after storms, impacts or alterations.

What to include in the written assessment

Get the document

Download the free risk assessment template (Word) and fill in the table above for your job, or have the RAMS generator produce a completed risk assessment and method statement for this trade in Word for £19.

Questions

Who can inspect a scaffold?

A competent person — someone with the training, knowledge and experience for that type and complexity of scaffold. The user or hirer is responsible for making sure the inspections happen.

Does a scaffold always need a design?

It needs either a generally recognised standard configuration (TG20, or the manufacturer's instructions for system scaffolds) or a bespoke design proven by calculation. There is no third option.

Need the finished document, not just the guide?

Answer a few questions about the job and get a completed RAMS in Word, ready to send — £19 including VAT, supplied straight after payment.

Build my RAMS — £19

Also as editable Word files, £9 each: Method statement template · Health and safety policy template.