Roofing risk assessment and method statement

Falls from roofs are among the biggest killers in construction, and HSE is clear that even a job measured in minutes is highly dangerous. A roofing RAMS has to answer three questions before anyone sets foot on the roof: how do we stop a fall from the edge, how do we stop a fall through the surface, and how do we get up there safely. This page gives the hazards and controls for the risk assessment half and the sequence for the method statement half.

Based on HSE — Roof work, read 2026-10-18. This page is a starting point you must adapt to your own site, people, equipment and the client's rules. It is not a substitute for an assessment by a competent person.

Hazards and controls

HazardWho is at riskControls
Falls from the roof edgeRoofersScaffolding on sloping roofs; edge protection at the eaves — front and rear on terraced properties; a secure double guardrail with toeboard around flat roofs.
Falls through fragile surfacesRoofersTreat every roof as fragile until a competent person confirms otherwise; a platform beneath the roof where possible; otherwise stagings, guard rails, fall restraint or fall arrest, and safety nets slung close beneath the roof.
Falls through fragile rooflightsRoofersRooflights are hard to see in some light and may be painted over — barriers or covers that are secured and labelled with a warning.
Falls through openingsRoofers, other tradesOpenings covered or guarded as soon as they are formed; covers fixed and marked.
Unsafe access to and along the roofRoofersAccess planned, especially where work moves along the roof: general access scaffold, stair tower, scaffold tower, mobile access equipment, roof access hatch, or a properly secured ladder and roof ladder for short-duration work.
Falling materialsPublic, other tradesDebris chutes, covered walkways or exclusion zones below; nothing thrown from the roof.

Method statement — sequence of work

  1. Roof type, pitch and surface condition confirmed by a competent person from the ground and from the access point before work starts.
  2. Edge protection or scaffold erected and inspected; nets or platforms installed where the surface is fragile.
  3. Materials lifted by hoist or passed up a scaffold, not carried up ladders; stacked away from the edge.
  4. Work stopped in high winds, ice or heavy rain; the sequence runs from the ridge down on strip-outs so nobody works below loose material.

What to include in the written assessment

Get the document

Download the free risk assessment template (Word) and fill in the table above for your job, or have the RAMS generator produce a completed risk assessment and method statement for this trade in Word for £19.

Questions

Can a ladder be used for roof work?

For short-duration tasks measured in minutes, a properly secured ladder and a proper roof ladder may be used. Anything longer needs a scaffold, tower or other access equipment.

Is a method statement required for roofing?

There is no law naming the document, but the Work at Height Regulations 2005 require the work to be planned, supervised and carried out safely, and clients and principal contractors routinely ask for a RAMS as the evidence of that planning.

Need the finished document, not just the guide?

Answer a few questions about the job and get a completed RAMS in Word, ready to send — £19 including VAT, supplied straight after payment.

Build my RAMS — £19

Also as editable Word files, £9 each: Method statement template · Health and safety policy template.